We understand this revelation (so to speak) is likely too late for many contractors that have already established final indirect rates for the year of PPP forgiveness; however, any direct costs adjusted for loan forgiveness still remain open until closeout of the contract.
John C. Shire, CPA
Recent Posts
Apparently, nothing the Board found was to the liking of the judges at the United States Court of Appeals for the Federal Circuit in Case Number 21-2304, Secretary of Defense v. Raytheon Company, Raytheon Missile Systems, decided January 3, 2023. This was the appeal from the Armed Services Board of Contract Appeals in Nos. 59435, 59436, 59437, 59438, 60056, 60057, 60058, 60059, 60060, and 60061.
Topics: Incurred Cost Proposal Submission (ICP/ICE), Government Regulations, Federal Acquisition Regulation (FAR)
In the Lockheed Martin ASCBA Case 62209 Lockheed Martin Aeronautics Company April 13, 2022 Decision, the Board found that when there is a Congressionally established statute of limitation the “theory of laches” does not apply.
Topics: Government Regulations, Federal Acquisition Regulation (FAR)
In the ASCBA Case 61691 Doubleshot, Inc. July 19, 2022 Decision, the Board supported what we believe is the correct reading of the records retention requirement under the FAR related to Cost-Reimbursable contracts. FAR 52.215-2, Audit and Records, requires contractors to make available until 3 years after final payment or any shorter period specified in Subpart 4.7.[1] FAR 4.705-2(b) limits the required retention period to 2 years from the end of fiscal year for pay related records (e.g., timesheet or cards).[2] So provided you submit your Incurred Cost Submission (required by FAR 52.216-7, Allowable Cost and Payment Clause) on time, you only need to maintain any of the records listed in FAR Subpart 4.7 for the time period set forth in that section of the FAR.
Topics: Contracts & Subcontracts Administration, Government Regulations, Federal Acquisition Regulation (FAR), Material Management and Accounting System (MMAS), Estimating System Compliance
Recent Armed Services Board of Contract Appeals (ASBCA) cases have rejected contractor requests for equitable adjustments (REAs) related to the impact of COVID-19 on contract performance under firm fixed price (FFP) contracts. In both cases, discussed below, the ASBCA turned to the Connor Bros. Federal Circuit decision (550 F.3d 1368 (2008)). In that decision the Federal Circuit found the act of the Sovereign Government does not result in an act of the Government as a contracting party. Therefore, under the “Changes” clause (FAR 52.243-1, Changes-Fixed-Price) that was in Connor’s contract this did not give rise to an equitable adjustment in the contract price. The basis of the Connor Bros. decision and the two recent cases is the “Sovereign Acts Doctrine.”
Topics: Government Regulations, COVID-19, Federal Acquisition Regulation (FAR)
Government Contractor Purchases below the Micro-Purchase Threshold Require NO Documentation
This is a common misconception within the GOVCON community. While the expectations are clearly less documentation and effort are required than that of a larger dollar value purchase, there is not a magic threshold at which NO documentation of the fair and reasonable price is allowed.
Topics: Compliant Accounting Infrastructure, Incurred Cost Proposal Submission (ICP/ICE), Contracts & Subcontracts Administration, DFARS Business Systems, DCAA Audit Support, Contractor Purchasing System Review (CPSR), Government Regulations, Federal Acquisition Regulation (FAR), Estimating System Compliance
The Government runs away to fight another day and another day.
What is this Groundhog Day?
L3 Technologies, Inc. (L3) takes the Government to task[1] for “challenging both indirect and direct costs paid to L3 on several government contracts for certain years.” During the long-drawn-out process of the litigation, “the government apparently thought better of its claims and withdrew them in toto[2] and represented it would make no further claims on the contract years in question.” L3 opposed, the dismissal seeking either summary judgment in its favor or that the Board “keep the appeals live so that it can obtain a victory that, it believes, would preclude its suffering similar government claims in other contract years.” No such luck, the Board granted the government’s motion and dismissed the appeals.
All we can hope is that someday the fox will get the gingerbread man (aka the Government) and this Groundhog Day nightmare will stop.
[1] Armed Services Board of Contract Appeals (ASBCA) Case Nos. 61811, 61813, and 61814
[2] Fancy Latin word for completely.
Topics: Incurred Cost Proposal Submission (ICP/ICE), Contracts & Subcontracts Administration, DCAA Audit Support, Government Regulations, Federal Acquisition Regulation (FAR)
Lockheed Martin raised a great question to the ASBCA as to “whether the Fly America Act, 49 U.S.C. § 40118 (FAA) and Federal Acquisition Regulation (FAR) 52.247-63 only apply to direct personnel performing direct work on covered contracts, or also applies to indirect personnel or indirect travel.”[1] The Board declined to hear the case as there was no “live dispute” at hand.
[1] Armed Services Board of Contract Appeals Case No. 62377
Topics: Compliant Accounting Infrastructure, Incurred Cost Proposal Submission (ICP/ICE), Contracts & Subcontracts Administration, DCAA Audit Support, Government Regulations, Federal Acquisition Regulation (FAR)
At the end of each of the DCAA audit programs for contractor business systems, DCAA discusses what it refers to as “Less Severe Significant Deficiencies.” These are clearly deficiencies which do not meet the DFARS definition of a “Significant deficiency.”[1] As a result, the withhold requirement provided for in DFARS 252.242-7005 cannot be applied.
Topics: Compliant Accounting Infrastructure, Contracts & Subcontracts Administration, DFARS Business Systems, DCAA Audit Support, Contractor Purchasing System Review (CPSR), Government Regulations, Federal Acquisition Regulation (FAR)
DCAA issued some guidance on PPP forgiveness treatment in the form of frequently asked questions (FAQs) to its auditors. The FAQs were not front and center on DCAA’s website but search on “PPP” did find them at: COVID FAQ for PWS 07142021 (dcaa.mil).
Topics: Compliant Accounting Infrastructure, Incurred Cost Proposal Submission (ICP/ICE), Small Business Compliance, Contracts & Subcontracts Administration, DCAA Audit Support, Defense Procurement and Acquisition Policy (DPAP), Government Regulations, COVID-19, Paycheck Protection Program (PPP) Loans, Federal Acquisition Regulation (FAR)