Does the Total of All Proposed Subcontract Costs Exceed 70% of the Total Contract Costs?
Is your company submitting a proposal to the government/prime contractor that includes a total of all subcontract costs exceeding 70 percent of the total costs proposed? If so, you must identify “added value” in your proposal so the government/auditor does not classify the indirect cost applied to the total subcontract cost as “excessive pass-through charges.” The government considers indirect costs and profit/fee that a contractor applies to subcontract costs that exceed 70 percent of the contract to be “pass through costs.” This applies to lower tier subcontract costs also. If there is no negligible value added by the contractor, the government or auditor will question the indirect costs and profit/fee applied to the subcontract costs as unallowable excessive pass through under FAR 31.203(i).