RGCI - Are Government Contractors Delivering Work for Free Without a Consent to Subcontract

Government contractors can deliver work that supports a contract and still face disallowed subcontract costs when required written consent is missing. Purchasing system approval and exemptions from other regulatory requirements do not necessarily remove this obligation, making contract terms and approval documentation critical to cost recovery.

Federal Acquisition Regulations (FAR) contract clause 52.244-2, Subcontracts, requires that prime contractors, without an approved purchasing system, MUST obtain consent to subcontract. Consent to subcontract is a “Contracting Officer’s written consent for the Contractor to enter into a particular subcontract.” (Emphasis Added) Even with an approved purchasing system, the clause can list subcontracts the Governments wants to approve. Many contracting officers are overwhelmed and consent to subcontract is low on their priority list. After all, most contracting officers develop a level of trust with the contractors they deal with on a regular basis. Our friends at the Defense Contract Audit Agency (DCAA) are never going to allow common sense to get in the way of a possible audit finding.

FAR 52.244-2 is required in all cost-reimbursement contracts, labor-hour contracts, time-and-material contracts, and letter contracts that exceed the simplified acquisition threshold. Additionally, the clause will be in your fixed-price contracts that exceed the simplified acquisition threshold, requiring consent until the final fixed price is determined (i.e., a letter contract or if you are going to negotiate and award a subcontract before you agree on price with the Government, you will need consent).

What is an Approved Purchasing System?

An approved purchasing system is “a Contractor’s purchasing system that has been reviewed and approved in accordance with” FAR part 44, Subcontracting Policies and Procedures. FAR 44.301 addresses the requirements of a Contractor Purchasing System Review (CPSR). FAR 44.301-2 requires:

  • The contracting officer to perform a risk assessment as to whether a CPSR should be performed;
  • Once a CPSR is performed the contracting officer will determine if another CPSR is needed, at least every three years;
  • The contracting officer is to monitor the contractor’s management of its purchasing system; and
  • The contracting officer should have a monitoring plan.

FAR part 44 does not provide a specific set of criteria (i.e., requirements) that a contractor’s purchasing system should be in compliance with. If you have Department of War (DoW) contracts, Defense FAR Supplement (DFARS) 252.244-7998(c) does provide a listing of required system criteria. Other federal agencies (e.g., Department of Energy (DoE)) use the DoW criteria even if they were not incorporated into your contract.

What is the Risk?

Just more paperwork the Government will never bother to look at, right? While that is a possibility, let me tell you a story about what happened to one government contractor.

Technology Systems, Inc. (TSI) discovered the risk the hard way in Armed Services Board of Contract Appeals (ASBCA) 59577. On appeal, a four-judge panel found that the Government (i.e., Administrative Contracting Officer, ACO) had properly disallowed the entire amount of subcontracts where TSI had not obtained written consent. The board states: “It is undisputed that the direct costs of the two subcontracts challenged by the ACO and remaining at issue were, contrary to the terms of the FAR (as incorporated into TSI's contracts), not pre-approved by the ACO.” TSI had the Contracting Officer’s Technical Representative (COTR) perform an after-the-fact review that found the subcontracts to have been performed in support of the statement of work. The Board goes on to state: “we entertain little doubt that the subcontracts were performed pursuant to the statements of work of the contracts and were thus allocable costs.” The Board found that the reasonableness of the cost of the subcontracts had not been addressed which “is fatal to TSI' s attempts to provide an after-the-fact justification of these subcontracts.” This resulted in the prime contractor not being reimbursed for scope of work delivered by the subcontractor due to the lack of consent to subcontract. One would think that this action would be found to be “arbitrary and cupreous” on the part of the Government; however, the ASBCA did not find it so.

What if You are a Non-Traditional Defense Contractor?

While Non-Traditional Defense Contractors (NTDCs) are exempt for FAR part 31 and FAR 31.201-3 determining reasonableness, your contracts are still going to include FAR 52.244-2 requiring consent to subcontract. Back to our friends at DCAA. With them losing work related to NTDCs, they would love nothing more than to tick and tie your subcontracts to written documents from the contracting officer. No written consent the entire amount of the subcontract will be questioned. Bells will be ringing all over the DCAA universe. Hopefully you do not have an auditor working remotely in your neighborhood.

What Should Government Contractors Do?

Government contractors should:

  • Review your policies and procedures to ensure the FAR 52.244-2 requirement for consent to subcontract is properly addressed;
  • Provide training for your contracts and purchasing staff on the FAR 52.244-2 requirement;
  • Add language to your requests for consent that if the contracting officer fails to reply within a reasonable number of days (e.g., 15-days) you will consider it a breach of contract and submit a claim for any future disallowed costs.

Have your General Counsel provide input on this last suggestion.

Addressing Consent Requirements Before Subcontract Award

Redstone Government Consulting assists government contractors in reviewing contract clauses and purchasing procedures to identify when consent to subcontract is required and how those requirements are addressed before award. Our team reviews requests for consent to subcontract, supporting documentation, and subcontract files for documentation gaps and assists with developing procedures that clarify responsibility for requesting, tracking, and retaining written approvals. Training for contracts and purchasing personnel reinforces those procedures so consent requirements are considered as part of subcontract planning and award.

Written by John C. Shire, CPA

John C. Shire, CPA John is a Director with Redstone Government Consulting, Inc. providing government contract consulting services to our clients primarily related to the DFARS business systems, CAS Disclosure Statements, and DCAA/DCMA compliance preparation, advisory, and defense. Prior to joining Redstone Government Consulting, John served in a number of capacities with DCAA/DCMA for more than 30 years. Upon his retirement, he was based in Texas as an SES-level Corporate Audit Director for DCAA, managing a staff of 300 auditors at one of the largest DOD programs. Professional Experience John began his career in the late 80s working in the Clearwater, FL audit office and over the next three decades he progressed through a number of positions within both DCAA and DCMA with career highlights as DCAA Program Manager at Ft. Belvoir, Chief of Technical Programs Division, Deputy Assistant Director-Policy, Director of the DCMA Cost and Pricing Center, the SES-level Lockheed Martin Corporate Audit Director, and Director of Integrity and Quality Assurance. John’s three decades of experience in performing and leading DCAA auditors and DCMA reviewers provides a wealth of expertise to our clients. John’s role, not only in the performance of audits, but also in the development of audit policy affords him unique insights into the defense of audit findings and the linkage of audit program steps to the underlying regulatory framework. He is an expert in FAR, DFARS, and other agency acquisition regulation, as well as a subject matter expert in the Cost Accounting Standards having reviewed and provided audit feedback on many of the largest and most complex cost accounting practices during his tenure with the DCAA. John’s tenure with DCAA and DCMA came at a critical time during each agency’s history where a number of changes were occurring such as the response to the ICS backlog, development of audit approaches to the DFARS Business Systems and implementation of new audit initiatives as a result of Congressional oversight through the NDAA process. John’s leadership at the DCMA Cost & Pricing center saw oversight of all major DOD pricing actions, leadership of should cost review teams, the Commercial Pricing group and many other areas of strategic value to our clients. His involvement in these and other Agency initiatives is of great value to our clients due to his in depth understanding of DCAA and DCMA’s internal policy directives. Education John holds a Master of Business Administration and a B.A. in Accounting from the University of South Florida. Certifications Certified Information Systems Auditor State of Alabama Certified Public Accountant

About Redstone GCI

Redstone GCI is a consulting firm focused on fulfilling the needs of government contractors in all areas of compliance. With a singular mission to help contractors through the multiple layers of “red tape,” we allow contractors to focus on what they do best – support their mission with the U.S. Government. We are home to a group of consultants made up of GovCon industry professionals, CPAs, attorneys, and retired government audit and acquisition professionals.

Our focus and knowledge of audit and compliance functions administered by DCAA and DCMA will always be at the heart of what we do. However, for the past decade, we’ve strategically grown to support other areas of the government contractor back-office with that same level of focus and expertise. We’ve added expertise in contracts management, subcontract administration, proposal pricing, various software systems, HR and employment law, property administration, manufacturing, data analytics/reporting, Grant specialists, M&A, and many other areas. When we see a trend in the needs of contractors, we act to ensure we can provide the best expertise in the market to fulfill those needs.

One thing our clients can be certain of is that with the Redstone GCI Team in your corner, there is no problem too big and no issue too technical for our team to tackle.

Topics: Contracts & Subcontracts Administration, DFARS Business Systems, DCAA Audit Support, Contractor Purchasing System Review (CPSR), Government Regulations, Federal Acquisition Regulation (FAR)