Redstone_-_When_a_Firm-Fixed-Price_Contract_Becomes_a_Curse-Social

Sometimes, a company is so anxious to receive a government contract that it ignores warning signs in the solicitation and accepts a firm-fixed-price contract when the contract type is not appropriate for the circumstances. Often the warning signs are subtle and consist of vague specifications, but in other cases, the warning signs are written, literally in capital letters. One such contract resulted in the ASBCA issuing a decision on March 30, 2016, on case number 58243. This case upheld a termination for default issued April 23, 2012, against Highland Al Hujaz Co., Ltd. This case illustrates both the warning signs the contractor should have heeded and the consequences.

In February 2009, the Corps issues a solicitation for a firm fixed price (FFP) contract for design and construction of an ANA Corps Support Battalion (CSB) to accommodate 700 soldiers initially and ultimately accommodate 1,640 soldiers. The installation was to be located adjacent to the ANA Garrison at Camp Hero in Kandahar, Afghanistan. It included soldiers’ barracks, the dining facility, and several priority life-support systems, which included electrical power system.

There were many warning signs in the procurement process which should have alerted Highland that a FFP contract would be a high risk for them in this particular procurement. The solicitation included the following statements which clearly put all risk of non-performance on the contractor:

  • “If the power system is not completed by September 01, 2009 the contractor will be required to supply temporary power to the compound.”
  • “Costs incurred in the performance of project execution that arise from the attacks of hostile entities, such as costs arising from damage to or destruction of contractor equipment and facilities, and damage to or destruction of project prior to Government acceptance, are the sole responsibility of the contractor. The Government makes no guarantee to provide the contractor with security, and bears no obligation to reimburse the contractor for costs arising from the attacks of hostile entities. When appropriate, the Contracting Officer may provide the contractor with an equitable adjustment with respect to time - but not cost.”
  • “It is recognized by the parties entering into this contract that performance ... will take place in Afghanistan. Afghanistan has been designated ... as an area in which Armed Forces … are … engaged in combat.... circumstances may cause the contemplated project to be [a]ffected during said performance. Examples… circumstances include … Outbreak of hostilities in or near the project site….”
  • “If the contractor believes he will not have the life support facilities completed by the Soldier move-in date, then he should include the temporary facilities cost into his bid proposal.”
  • “THE CONTRACTOR MUST BID UPON THIS PROJECT KNOWING ALL RISKS ASSOCIATED WITH CONSTRUCTION IN AFGHANISTAN. SUCH RISKS FAR EXCEED HOSTILITIES. NO SPECIAL CLAUSE IS TO BE ADDED; THE CONTRACTOR IS RESPONSIBLE FOR ALL ACTIONS, INCLUDING DELAYS FROM HOSTILITIES, ETC[.] AND SHOULD REFLECT THIS RISK IN HIS BID. THE PURPOSE OF THE DESIGN-BUILD CONTRACT IS TO REFLECT SUCH RISKS UPON THE CONTRACTOR AND NOT THE GOVT[.]” (Capitalization is from the original document.)

Negative impacts during contract performance included:

  • Severe flooding in November 2011
  • The Afghanistan government's expulsion of skilled Pakistani workers in the fall of 2011
  • Closure of the border between Afghanistan and Pakistan from November 2011 through July 2012, which resulted in a "freight embargo"
  • The hijacking of critical transformers along the Pakistani border in November 2011
  • Security issues

As for the consequences:

  • The court determined the termination for default was justified
  • Highland now has a termination for default on its record, which will seriously hinder any attempt to receive further government contracts
  • There are also cases pending where the government asserted government claims for excess re-procurement costs, overpayments during performance, and liquidated damages under this contract
  • The 420 day performance period spiraled into almost three years
  • ASBCA cases still ongoing over four years after the termination for default

In short, do not be over-eager to receive a FFP contract that shifts too much of the risk from the Government to your company. You might get it!   Lastly, if you believe that the Government will agree to a FFP to cover all of the contingencies, good luck with those negotiations.

Contact Us for a Consultation

Written by Redstone Team

About Redstone GCI

Redstone GCI is a consulting firm focused on fulfilling the needs of government contractors in all areas of compliance. With a singular mission to help contractors through the multiple layers of “red tape,” we allow contractors to focus on what they do best – support their mission with the U.S. Government. We are home to a group of consultants made up of GovCon industry professionals, CPAs, attorneys, and retired government audit and acquisition professionals.

Our focus and knowledge of audit and compliance functions administered by DCAA and DCMA will always be at the heart of what we do. However, for the past decade, we’ve strategically grown to support other areas of the government contractor back-office with that same level of focus and expertise. We’ve added expertise in contracts management, subcontract administration, proposal pricing, various software systems, HR and employment law, property administration, manufacturing, data analytics/reporting, Grant specialists, M&A, and many other areas. When we see a trend in the needs of contractors, we act to ensure we can provide the best expertise in the market to fulfill those needs.

One thing our clients can be certain of is that with the Redstone GCI Team in your corner, there is no problem too big and no issue too technical for our team to tackle.

Topics: Proposal Cost Volume Development & Pricing